Saudi data centre operators expect to wait an average of nine months for additional grid capacity to scale artificial intelligence workloads, according to a 2026 study by Fluke Corporation. That is the shortest expected wait among the six countries surveyed and three months below the global average of 12 months.
Operators in Germany expect to wait 11 months, while those in France, the US and India anticipate 13 months. The UK has the longest expected wait at 14 months.
The study, conducted by Censuswide for Fluke, surveyed 1,300 data centre professionals, including 200 in Saudi Arabia. It found that 82% of Saudi respondents believe their cooling and electrical systems are well or very well equipped for projected AI workloads during extreme heat. Another 76% said their electrical infrastructure is fully or largely ready for AI and high-performance computing.
However, gaps remain. Only 47% reported comprehensive or extensive real-time visibility across critical electrical systems, while 52% said recruiting qualified electrical technicians was difficult.
Saudi AI company HUMAIN plans to deploy 3GW of AI data centre capacity by 2030. It also has a financing framework of up to $1.2B with the National Infrastructure Fund for up to 250MW of hyperscale capacity.
Source: Middle East AI News